Zwickau
Magistrates’ Court
Zwickau, Germany / 04.2024 - 07.2024
The new headquarters of Zwickau Local Court combines historic building fabric with modern architecture. As part of the extension and modernisation project, the Berlin branch of PORR special civil engineering Ost was commissioned to carry out rehabilitation and stabilisation work. The focus was on improving the subsoil conditions for the extension and securing the existing building, which is of architectural and historical value.
Facts & Figures
Company
PORR Spezialtiefbau GmbH
Type
Subsoil improvement
Runtime
04.2024 - 07.2024
Existing system gains new functions
Built in 1853 in the Neo-Renaissance style, the magistrates’ court has served a variety of purposes over the years. After initially functioning as a courthouse, it served as the town hall and, at times, housed the registry office and the tax office. The historic building is due to be extended and comprehensively modernised by the end of 2027.
Stable subsoil over an area of around 900 square metres
On behalf of SP Bau GmbH from Lengenfeld, PORR special civil engineering Ost undertook the work to stabilise the subsoil. Over an area of around 900 m², the team carried out ground improvement using the jet grouting method. This created the conditions necessary for the safe foundation of the extension’s floor slab.
Underpinning secures the historic building
In addition to the ground improvement, the immediately adjacent existing building required special stabilisation measures. The foundations of the historic building were underpinning with a total of around 680 m³ of high-pressure grout. This is intended to prevent subsidence and settlement resulting from the new construction.
Low-vibration work in the immediate vicinity of the building
The work had to be carried out in such a way that the historic building structure remained as unaffected as possible. The jet grouting method used enables low-noise and vibration-free execution. This made the method suitable for work in the immediate vicinity of the existing building.
Additional measures in the groundwater zone
A further constraint arose from the new building’s location within the groundwater zone. In addition to the services provided by PORR special civil engineering, additional measures were therefore required by the client. These included sheet pile walls and groundwater lowering.
New premises for the District Court
With this extension and modernisation, the historic building is being developed for its future use as the main administration centre of the Zwickau District Court. The extension, the new atrium with two courtrooms and the modernisation of the existing building create the necessary spatial conditions for this.