PORR Verkehrswegebau installed a newly developed asphalt base course for the Slab Track Austria slab track system on a section of the Stuttgart 21 project. The Münster branch carried out the work on behalf of the ARGE FF PORR S21 consortium and in coordination with DB InfraGO AG. With this new structure, an asphalt base course replaced the concrete base course and hydraulically bound base course that had previously been planned.

Picture shows 2 construction workers from behind in one of the S21 tunnels.
© ARGE FF PORR S21

Facts & Figures


Company

PORR Verkehrswegebau GmbH

Type

Slab Track Austria

Runtime

06.2024 - 03.2025

Principal
ARGE FF PORR S21

Asphalt base course for the slab track on the Stuttgart 21 project

33 kilometres of slab track

As part of the ATCOST21 consortium, PORR had already completed the approximately 9.5-kilometre-long twin-tube Filder Tunnel, the approximately 5.7-kilometre-long twin-tube Obertürkheim Tunnel and the just over one-kilometre-long Untertürkheimer Kurve Tunnel. For the remaining works, PORR Austria and PORR Germany formed the FF PORR S21 joint venture. This joint venture took on the planning and construction of 33 kilometres of slab track, as well as the electrical equipment and cable laying.

Expertise in road and railway construction

For the installation of the asphalt base course, PORR’s railway construction specialists collaborated with PORR Verkehrswegebau. In particular, PORR Verkehrswegebau contributed its expertise in the field of asphalt technology.

Slab Track Austria as the basis

The basis for the construction was Slab Track Austria, also known as the ÖBB-PORR slab track system. The system, developed jointly by PORR and the Austrian Federal Railways, was first built in Langenlebarn, Austria, in 1989 and, at the time of the project briefing, had also been in use in Germany for more than 20 years. Unlike a conventional track superstructure, this was a ballastless superstructure.

Elastically supported track-supporting slabs

The central element of the system was an elastically supported track-supporting slab made of loosely reinforced concrete with integrated rail supports. An elastic separation layer was situated at the base of the slab and at the conical grouting openings, serving to provide structural decoupling and to reduce vibration and structure-borne noise. In the standard structure approved by the Federal Railway Authority, the track-supporting slab was installed on a substructure comprising a concrete base course and a hydraulically bound base course, and was grouted with self-compacting concrete following fine levelling.

Two base courses replaced by asphalt

For Stuttgart 21, the ARGE FF PORR S21 consortium developed a modified system structure. In this design, the planned asphalt base course replaced both the concrete base course and the hydraulically bound base course of the standard system. The new structure was first used on line 4703 in the Obertürkheim branch on an earth embankment as well as in trough and tunnel structures.

Special low-temperature asphalt

For the new base course, the project team used a special, low-temperature asphalt AC 22 T S 50/70 with a viscosity-modifying binder 30/45. The selection of the mix was prepared in advance through practical investigations. On a separate test section, the team examined both the structural behaviour of the material and its processing characteristics.

Testing prior to actual laying

Using the test area, the project team prepared for the subsequent use of the special mix under the intended conditions. This provided insights into the behaviour and workability of the asphalt base course. These insights served as the basis for the subsequent laying on the road section.

Use in various types of structures

A distinctive feature of the project was the variety of applications for the newly developed asphalt base course. The system was installed not only on an earthwork structure but also in trough and tunnel structures. Consequently, the method was utilised within the Obertürkheim branch under a range of structural conditions.

Part of the new rail infrastructure

The works formed part of line 4703 on the Obertürkheim branch and were thus an integral part of the Stuttgart 21 infrastructure project. The slab track laid there constituted part of the project’s new rail infrastructure.

PORR Deutschland: Stuttgart 21 Los C . Slab Track Austria auf Asphalttragschicht, Stuttgart

What ultimately counts in the construction business is successfully completed projects. PORR has many of these.