Foundations

Duisburg
Thyssenkrupp Steel

Duisburg, Germany / 01.2024 - 05.2025

On the thyssenkrupp Steel Europe site in Duisburg, PORR Spezialtiefbau, in a joint venture with Implenia Spezialtiefbau, is carrying out key foundation and special civil engineering works for a new direct reduction plant (DRI plant). The contract includes pile foundations using Franki piles, subsoil improvement using CMC columns, as well as one of the main base slabs for the 140-metre-high DRI tower. In addition, the scope of work comprises an excavation pit up to 14 metres deep, featuring a 4,200 m² watertight construction pit enclosure as well as a shoring system comprising in-situ concrete diaphragm walls.

The picture shows the construction site. In the background, you can see a power plant, several cranes and two drilling rigs.
© PORR

Facts & Figures


Company

PORR Spezialtiefbau GmbH

Type

Foundations

Runtime

01.2024 - 05.2025

Principal
thyssenkrupp Steel Europe AG

Foundation for thyssenkrupp Steel’s direct reduction plant

Transformation of steel production in Duisburg

With the first DRI plant on the works site in Duisburg’s Südhafen Walsum, thyssenkrupp Steel is driving forward the transformation of its steel production. In future, hydrogen is to be used instead of coke as a reducing agent in the production of pig iron. According to project details, the plant is expected to save up to 3.5 million tonnes of CO₂ per year and contribute to the goal of climate-neutral steel production by 2045.

Consortium brings together special civil engineering services

The ‘ARGE Spezialtiefbau DRI-Anlage’ consortium, comprising PORR Spezialtiefbau and Implenia Spezialtiefbau, was awarded the contract for the works. Following approval for an early start to construction on 15 January 2024, pile foundation work began in April 2024. In addition to the foundation work, the scope of works includes the construction of the CMC columns, extensive earthworks and the construction of one of the main base slabs for the 140-metre-high DRI tower.

1,100 Franki piles for the foundations

PORR special civil engineering is installing a total of around 1,100 Franki piles for the project, each with a diameter of 71 cm and lengths ranging from 9.5 to 12 m. By mid-September 2024, 561 of these piles had been installed and around 5,100 m³ of concrete had been used. The Franki piles replace a large proportion of the fully cased bored piles originally planned, which had diameters of between 1.2 and 1.8 m.

Less concrete and reinforcement thanks to the displacement method

By switching to Franki piles, the planned volume of concrete was reduced from 13,750 m³ to 4,750 m³. At the same time, the amount of reinforcement required was reduced by around two-thirds. As the Franki piles are constructed using the displacement method, there is also no need for drilling.

Slim cross-section for high loads

The driven pile base of the Franki piles enables them to bear greater loads whilst having a slimmer cross-section and improved settlement behaviour. This results in benefits in terms of material usage, construction time and costs compared with the originally planned fully-cased Kelly bored piles. In particular, the smaller pile diameter reduces the requirement for concrete and reinforcement and, consequently, the associated CO₂ emissions.

High driving resistances in the former storage area

The subsoil conditions on the factory site, which had been used for many years to store heavy steel products, presented a particular challenge. The resulting increased driving resistances had to be overcome during the construction of the Frankip piles. By mid-September 2024, approximately half of the pile foundation work had been completed.

Up to 14 m deep into the subsoil

In addition to the pile foundations, further extensive specialist civil engineering works form part of the contract. These include a construction pit up to 14 m deep with a watertight construction pit enclosure covering an area of around 4,200 m². The construction pit shoring is being constructed as a cast-in-situ diaphragm wall.

A key component of steel production in Duisburg

The DRI plant forms part of the transformation of steel production at the Duisburg site and is due to be completed in 2027. Once operational, it will use hydrogen as a reducing agent, thereby reducing CO₂ emissions from steel production by up to 3.5 million tonnes per year.