Back to overview
Rehabilitation

Hamburg
Quay wall at Kehrwiederspitze

Hamburg, Germany / 06.2026 - 04.2027

Through the rehabilitation of the quay walls at Kehrwiederspitze, PORR contributed to the preservation of a defining part of Hamburg’s Speicherstadt. PORR Spezialtiefbau, Northern Region, undertook the special civil engineering works for the next phase of the rehabilitation on behalf of the Kehrwiederspitze Quay Wall Refurbishment Consortium. The works were carried out to secure the quay walls – which are over 100 years old and listed as historic monuments – and the adjacent site.

An aerial view of a port city with modern architecture: in the foreground, a building site by the water featuring cranes, vehicles and ships; in the background, the striking Elbphilharmonie building, as well as red-brick buildings and high-rises along the river.
© PORR

Facts & Figures


Company

PORR Spezialtiefbau GmbH

Type

Rehabilitation

Runtime

06.2026 - 04.2027

Principal
ARGE Kaimauersanierung Kehrwiederspitze c/o Fr. Holst (GmbH & Co. KG)

PORR secured historic quay walls at Kehrwiederspitze in Hamburg

Construction between the Speicherstadt and the Elbphilharmonie

The construction site was situated in the immediate vicinity of the UNESCO World Heritage Site, the Speicherstadt, and within sight of the Elbphilharmonie. Numerous visitors passed by the construction site every day between the Landungsbrücken, the Speicherstadt and the Elbphilharmonie. At the same time, a new public leisure area was created at this prominent location.

32 large bored piles for Section 19

In Section 19, the team constructed back-anchored bored pile walls comprising a total of 32 large bored piles. The piles had diameters of 75 and 118 cm and reached lengths of up to 24 m. The work was carried out without causing vibrations and whilst construction site operations continued.

107 micro piles for the new retaining slab

The installation of the large bored piles was followed by the back-anchoring of the bored pile walls and the construction of a new reinforced concrete retaining slab. A total of 107 micro piles were specified for this purpose. Quality and safe execution were central to the client’s requirements.

Obstacles in the historic subsoil

The inner-city location and limited space placed particular demands on site organisation and execution. Added to this were various obstacles in the subsoil, including old timber piles, remnants of the historic quay wall and an old anchor that was no longer in use. These conditions had to be taken into account during the specialist groundworks.

Experience from an earlier construction phase

As early as 2022, the Hanover branch was involved in the rehabilitation of the historic quay walls. On behalf of FR. Holst GmbH, PORR installed 126 inclined piles for a section approximately 180 m long at Kehrwiederplatz. The experience gained there formed a valuable basis for the work at Kehrwiederspitze.

Continuation in Section 18

Following completion of the work in the first construction phase, the drilling rigs were fully dismantled in 2026. The return of the specialist civil engineering team for the second construction phase was scheduled for spring 2027. In Section 18, a further bored pile wall and additional micro piles were planned.

Construction site in a prominent neighbourhood

Directly adjacent to the construction site stood the striking brick building at Kehrwiederspitze 1. The building is known as Police Station 21 from the ZDF series ‘Notruf Hafenkante’ and, in reality, houses Port Police Station No. 2, which is the headquarters of the Water Police. This meant that the works were not only taking place in a historically significant setting, but also in a highly frequented and publicly visible area.

Preserving and repurposing historic urban space

The rehabilitation work secured the historic quay walls at a central location in Hamburg’s Speicherstadt. At the same time, a new public space was created between the Speicherstadt and the Elbphilharmonie, thereby providing an additional amenity at Kehrwiederspitze.

What ultimately counts in the construction business is successfully completed projects. PORR has many of these.