Between Görzke and the Riembach, the Berlin branch of PORR transport route engineering carried out refurbishment work on a section of the national road 94 on behalf of the Brandenburg State Roads Authority. The works involved renewing the asphalt surface from Belziger Straße in Görzke to the culvert over the Riembach. In future, the rehabilitated section will also serve an important function as a diversion route for upcoming construction work on Federal Road 107 in the Ziesar area.

A lorry is spreading coarse gravel or crushed stone onto a road to stabilise or repair the carriageway. The road is in a rural area with trees and houses in the background.
© PORR

Facts & Figures


Company

PORR GmbH & Co. KGaA

Type

State road

Runtime

03.2026 - 06.2026

Principal
Landesbetrieb Straßenwesen Brandenburg

The L 94 between Görzke and Riembach has been upgraded

New road surface over an area of approximately 20,300 m²

Construction work began in March 2026 and was completed on schedule at the end of June. The PORR team renewed the asphalt structure over an area of approximately 20,300 m². Around 7,000 tonnes of AC 22 TS were laid and a new SMA surface course was applied.

SAMI layer between the existing structure and the new asphalt surface

The so-called SAMI layer played a key role in the road structure. This thin intermediate layer connects the existing road structure to the new asphalt surface and helps to relieve stresses. At the same time, it prevents existing cracks from older layers from transferring into the new road surface, thereby enhancing the durability of the new road structure.

Digitally supported asphalt paving

The SSO digital system was used during the works. This enabled the asphalt paving process – from the asphalt mixing plant right through to compaction on site – to be digitally planned and monitored. The system supported the control and documentation of the individual process steps.

Key diversion route in the Ziesar area

Since the completion of the works, the resurfaced section of the L 94 has been fully open to traffic again. At the same time, the road provides the necessary infrastructure for traffic management during the forthcoming construction projects on the B 107 in the Ziesar area.

What ultimately counts in the construction business is successfully completed projects. PORR has many of these.