At the Emmerich container terminal, the land-side crane runway for new gantry crane systems is being installed on a new foundation. The Düsseldorf branch of PORR special civil engineering was awarded the contract by EUROVIA for the necessary pile foundation work. PORR special civil engineering Planning was responsible for the pile layout and detailed design, including the pile structural analysis.

The picture shows the crane runway. In front of it is a frame with the PORR logo.
© PORR

Facts & Figures


Company

PORR Spezialtiefbau GmbH

Type

Foundations

Runtime

11.2024 - 12.2024

Principal
EUROVIA Bau GmbH

New crane runway at the Emmerich Container Terminal

Tri-modal hub on the Rhine

Situated directly on the German-Dutch border, the Emmerich container terminal is a major hub for international freight and goods logistics. As a tri-modal hub, the site connects road, rail and inland waterway transport along the Rhine. Work on the new crane runway therefore took place in an environment where ongoing port operations had to be taken into account.

Settlement requires new foundations

Increasing settlement in the shallow foundations of the existing land-side crane runway had led to considerable wear and tear on the two gantry cranes. At the same time, the existing crane systems had reached the end of their service life and were replaced by modern gantry crane systems. A new foundation was therefore required for their crane runway.

44 Frankipiles NG® over 258 metres

The new crane runway was deep-founded over a length of 258 m using a total of 44 Frankipiles NG®. The piles have a diameter of 71 cm and a length of around 16 m. The work was carried out on the basis of the pile layout plan and the detailed design, including the pile structural analysis, provided by PORR special civil engineering.

Load-bearing layers beneath thick fill layers

The ground conditions posed particular challenges for the foundation works. The construction site area contained fill layers with thicknesses ranging from 5 to 7.5 m; beneath these lay alluvial loam as well as terrace sediments consisting of sand and gravel, extending down to the settlement horizon of the pile foundation. The deep foundation made it possible to transfer the loads from the new crane runway into this settlement horizon.

Eight metres of working space whilst operations continued

In addition to the ground conditions, it was above all the confined space that characterised the execution of the works. A working space merely 8 m wide was available for the works, immediately adjacent to an existing gantry crane. This remained in operation throughout the entire construction period.

Safety officer co-ordinates crane and construction site

The ongoing crane operations required special precautions during pile fabrication. A safety officer was therefore present on site at all times during the works, monitoring crane operations and helping to prevent collisions. This enabled the foundation works to be carried out alongside existing operations.

Work in the immediate vicinity of the Rhine

The proximity to the Rhine and to the groundwater also had to be taken into account during site set-up and execution. Hazardous substances were stored in sealed containers and additionally in spill trays to prevent contamination of the Rhine and the groundwater. A spill tray was also used when refuelling the machinery to collect any potential drips.

New crane runway for the Emmerich logistics hub

The Emmerich container terminal, situated on the German-Dutch border, connects road, rail and inland waterway transport. The new crane runway creates the conditions at the site for the deployment of the new gantry crane systems.