Back to overview
Turnkey construction pits

Monheim
DSV works for the K714 Cultural Refinery

Mohnheim, Germany / 09.2022 - 03.2023

In Monheim am Rhein, the former Shell barrel-filling hall, dating from 1914, is being converted into a cultural and events centre. Within the listed building complex, several new buildings are being constructed to house event spaces, catering facilities and infrastructure areas. For the construction pits required for this project, PORR special civil engineering, in a joint venture with Vennes Erd- und Tiefbau, carried out the DSV works, back-anchoring and buoyancy control measures.

Picture shows the construction site; 2 workers are standing at the end of the excavation pit; a narrow corridor leads into the excavation pit
© PORR

Facts & Figures


Company

PORR Spezialtiefbau GmbH

Type

Turnkey construction pits, Underpinning

Runtime

09.2022 - 03.2023

Principal
Monheimer Kulturwerke GmbH

Excavation safety and foundation works in a listed building

Construction pits for future use

The core of the work involved excavating a main construction pit with a floor area of around 1,600 m² and a depth of 6.2 m for the new event hall. Two further construction pits, with areas of 680 m² and 920 m², provide the foundation for additional building sections. To secure the existing buildings, around 7,000 m³ of DSV shoring and underpinning structures were installed. As well as this, approximately 3,700 m of temporary wire anchors were used for back-anchoring, and around 2,800 m of micro piles were installed to counteract uplift in the parts of the building close to the river.

Work under challenging conditions

The specialist civil engineering works were carried out in the immediate vicinity of historic buildings. Existing foundations, columns and, in some cases, thin walls required precise execution of the excavation shoring and foundation works. Furthermore, the works had to be adapted to the confined space within the listed historic building.

Laying the foundations for the K714 Cultural Refinery

The deep foundation works, back-anchoring and micro piles carried out created the conditions necessary for the subsequent structural work and the planned new buildings within the historic building complex. Even before the future event and meeting spaces became visible, the structural foundations for the site’s further development were laid underground.

What ultimately counts in the construction business is successfully completed projects. PORR has many of these.