Power line for Hansa Business Park

Münster, Germany / 09.2025 - 09.2027

The consortium consisting of PORR Verkehrswegebau, Heinz Bente, and Gerhard Rode Rohrleitungsbau is constructing a new 110-kV high-voltage cable route for the Hansa Business Park on behalf of Stadtnetze Münster. The project is a key component for the future energy supply of the innovation location and, in particular, the new battery research factory.

The picture shows a slightly curved road. The road surface is dark asphalt and appears damp in places. On both sides of the road are conspicuous red barriers, indicating construction work. There are narrow green strips on the left and right sides of the road. Industrial or commercial buildings can be seen in the background on the right, including a building with flagpoles and a tall, cylindrical tower or chimney.
© PORR

Facts & Figures


Company

PORR Verkehrswegebau GmbH

Type

Pipeline construction

Runtime

09.2025 - 09.2027

Principal
Stadtnetze Münster

Energy for the future: PORR builds power line at Hansa-BusinessPark Münster

With the commissioning of the battery research factory, the power demand at Hansa-BusinessPark will increase to up to 23 megawatts. To meet this demand, a new substation with a powerful 110-kV connection to the Münster power grid is being built. The plan is to lay a new power line approximately six kilometers long. The consortium is responsible for constructing the line, which will mainly be built using open construction methods as a traveling construction site in around 100 sections ranging from 50 to 200 meters in length.

Protective pipe laying with HDD and press drilling

The construction method will be predominantly open with shoring boxes, while closed methods such as HDD and press drilling will be used for railway and water crossings. A total of six HDD drillings and one press drilling under the DB route are planned. The socket pits will be constructed after completion of the empty pipe route. These pits will be used for the subsequent installation of the power cables. The Kappenberger Dam was widened in November 2024 to avoid a complete closure during the main construction phase.

Precision despite limited space

The work is being carried out under flowing traffic on short construction sections with limited space. Intersecting lines, varying soil conditions and a high groundwater level pose particular challenges.

With this project, PORR Verkehrswegebau is making an important contribution to the energy transition and to ensuring a sustainable infrastructure for Münster as a center of innovation.

What ultimately counts in the construction business is successfully completed projects. PORR has many of these.