Delmenhorst
Schönemoor Wind Farm
Oldenburg, Germany / 03.2026 - 08.2026
The construction of the Schönemoor wind farm in Lower Saxony presented particular challenges in terms of subsoil conditions and foundation engineering. For its long-standing client, Enercon GmbH, PORR special civil engineering developed a foundation solution for four wind turbines that was tailored to the local subsoil conditions. The scope of work also included the associated crane sites.
Facts & Figures
Company
PORR Spezialtiefbau GmbH
Type
Foundations
Runtime
03.2026 - 08.2026
Foundation solution for challenging subsoil conditions
Ten wind turbines in Schönemoor
The Schönemoor wind farm comprised a total of ten wind turbines. Organic soil layers such as peat and silt, as well as a high water table, determined the conditions for the foundation works. According to the operator, enercity, the wind farm was expected to generate electricity for more than 30,800 households and avoid up to 47,000 tonnes of CO₂ annually compared with the baseline scenario.
Combination of pile foundations and subsoil improvement
For the foundations, PORR special civil engineering employed a combination of Frankipiles NG® and pre-compacting the gravel. The pre-compacting of the gravel improved the ground conditions around the pile tips, enabling the planned pile embedment depth to be adjusted. Both methods were tailored to the existing ground conditions and the project-specific loads.
376 Frankipfähle for four wind farm sites
The Oldenburg branch manufactured a total of 376 Frankipfähle with lengths of up to 13.5 metres. The piles were installed both vertically and at an angle and supported the loads of the wind turbines. The required number of piles for the respective requirements was determined on the basis of the design.
Compacted gravel layer at the pile tips
In addition to the pile foundations, PORR special civil engineering carried out pre-compacting the gravel at the planned pile settlement depth. This created a compacted gravel layer above and below the pile tip. This supported load transfer and improved the ground conditions in this area.
Pipe sleeves in organic soft layers
The organic soft layers required additional measures during pile construction. Special pipe sleeves protected the fresh concrete during installation in these soil areas. This ensured that the piles were adapted to the existing ground conditions.
Integrity testing for quality assurance
For quality assurance purposes, selected piles were subjected to non-destructive testing following their construction. An integrity test was carried out for this purpose. This complemented the foundation works, which had been tailored to the specific ground conditions.
Concept for the Schönemoor site
Drawing on experience from previous wind farm foundation projects, PORR developed a concept tailored to the project-specific requirements at Schönemoor. The pile system, pile arrangement and subsoil improvement were coordinated accordingly. On this basis, PORR special civil engineering carried out the foundation works for four of the ten wind turbines.
Wind energy for more than 30,800 households
According to the operator, enercity, the Schönemoor wind farm is expected to generate electricity for more than 30,800 households. Compared with the baseline scenario, this is expected to prevent up to 47,000 tonnes of CO₂ emissions annually.