Dortmund
Emscherallee
Dortmund, Germany / 01.2019 - 12.2020
In October 2018, subsidence and deformation of the carriageway were detected on Emscherallee in Dortmund, leading to the closure of a section of the road. This subsequently resulted in a sinkhole covering an area of around 500 m². During the investigation into the cause, it was found that the manholes of an existing DN 1600 sewer had become filled with soil. PORR special civil engineering was commissioned to carry out the jet-blasting work as part of the subsequent remediation measures.
Facts & Figures
Company
PORR Spezialtiefbau GmbH
Type
Rehabilitation
Runtime
01.2019 - 12.2020
DSV works to repair the sewer following a sinkhole
Construction pit for sewer rehabilitation
A watertight construction pit was designed for the sewer rehabilitation. The construction pit concept comprised a shoring system consisting of overlapping bored pile walls as well as a watertight foundation base constructed using the jet grouting method (DSV). In addition, DSV sealing slabs were constructed, which in some areas also performed structural functions within the excavation structure.
DSV sealing slabs and sealing walls
The trough-shaped excavation had a volume of approximately 2,214 m³. For the waterproofing, DSV elements with diameters of 2.0 m and depths of up to 18 m were installed. The total DSV volume amounted to around 1,957 m³. The jet lengths reached up to 12.64 m. The sealing walls were arranged around the existing sewer and complemented the construction pit’s waterproofing concept.
High demands on construction precision
Owing to the depth at which the DSV elements were installed, strict requirements regarding the positional accuracy of the boreholes had to be met. The drilling starting points were surveyed and the position of the adjacent elements coordinated in accordance with the construction plans. The excavation pit design required precise coordination between the sealing walls, the DSV base and the existing sewer structures.
Site logistics for DSV works
In addition to the jet grouting works, site logistics posed particular challenges for the execution of the works. For the production of the DSV bodies, cement slurries had to be delivered, as well as the backflow generated during the process had to be collected and discharged. The organisation of material flows and backflow disposal formed an integral part of the construction work.
DSV method for construction pit rehabilitation
The Stump-Jetting method, introduced by the building authorities, was used for the construction pit. The DSV base and the sealing walls, together with the shoring, formed the foundation for the rehabilitation work on the sewer structure.
Basis for the sewer rehabilitation
The construction of the DSV sealing slabs and the DSV sealing walls created the conditions necessary for the rehabilitation of the damaged section of sewer on Emscherallee. The specialist civil engineering works formed the basis for the subsequent measures within the watertight construction pit.