Velbert
L924 Fellerstrasse
Velbert, Germany / 03.2022 - 06.2022
Im Sommer 2021 kam es entlang der Landesstraße L924, der Fellerstraße in Velbert, zu erheblichen Schäden infolge eines Starkregenereignisses. Der parallel zur Straße verlaufende Felderbach führte während des Hochwassers große Wassermengen, wodurch Teile des Straßenkörpers unterspült wurden. Infolge der Schäden verlor der Hangbereich an Stabilität und die Böschung brach teilweise ab. Im Zuge der anschließenden Sanierung wurde der PORR Spezialtiefbau mit der Sicherung des Hangs sowie vorbereitenden Maßnahmen für die Wiederherstellung des Straßenabschnitts beauftragt.
Facts & Figures
Company
PORR Spezialtiefbau GmbH
Runtime
03.2022 - 06.2022
Slope stabilisation using soil nailing and a shotcrete shell
Rehabilitation works along the Felderbach stream
The damaged section was located immediately adjacent to the course of the Felderbach stream. In addition to restoring the stability of the road structure, further safety measures were required along the slope. In the central section of the route, a tangential bored pile wall was also planned to protect the road structure from further impacts from the watercourse in future. Before further roadworks could begin, the slope first had to be stabilised and prepared for the subsequent construction phases.
Soil nailing with a shotcrete lining
To temporarily stabilise the slope, it was first excavated to a depth of around 5 m. The slope was then stabilised using soil nailing with a shotcrete lining. The slope stabilisation was carried out in a total of four work layers. Each layer was stabilised using 7.25 m long ground nails, which were embedded in a 25 cm thick reinforced shotcrete shell. The shotcrete structure was adapted to the existing slope geometry and forms the basis for further work on the slope.
Work under constrained conditions
Only limited working space was available along Fellerstraße for the construction of the planned bored pile walls. Consequently, the stabilisation measures had to be carried out initially above the area where construction work would later take place. Furthermore, site logistics were influenced by local conditions. Due to land ownership issues, it was not possible to construct an access road on the valley side. The entire construction site was therefore accessed and supplied via Fellerstraße. Material transport, movement of equipment and work processes were adapted to the available space.
Preparations for the subsequent construction phases
The Soil nailing and the shotcrete lining served to stabilise the slope during the subsequent work on the road and the civil engineering structures. Step by step, this laid the foundation for the further measures to restore Fellerstraße, as well as for the subsequent construction of the bored pile walls in the area of the damaged section.
Foundation for the road’s rehabilitation
Even before traffic can use the route again, the embankment areas have been stabilised and the conditions for further construction work have been created. The installation of the Soil nailing, the shotcrete lining and the preparatory safety measures have laid the foundation for the rehabilitation of the L924 in Velbert. This marks the restoration of a further section of the transport infrastructure along the Felderbach.