Velbert
L924 Fellerstrasse

Velbert, Germany / 03.2022 - 06.2022

Im Sommer 2021 kam es entlang der Landesstraße L924, der Fellerstraße in Velbert, zu erheblichen Schäden infolge eines Starkregenereignisses. Der parallel zur Straße verlaufende Felderbach führte während des Hochwassers große Wassermengen, wodurch Teile des Straßenkörpers unterspült wurden. Infolge der Schäden verlor der Hangbereich an Stabilität und die Böschung brach teilweise ab. Im Zuge der anschließenden Sanierung wurde der PORR Spezialtiefbau mit der Sicherung des Hangs sowie vorbereitenden Maßnahmen für die Wiederherstellung des Straßenabschnitts beauftragt.

Picture shows the work on the L924 Fellerstraße, Velbert. Slope stabilisation with soil nailing and shotcrete formwork
© PORR

Facts & Figures


Company

PORR Spezialtiefbau GmbH

Runtime

03.2022 - 06.2022

Principal
Heitkamp Erd- und Straßenbau GmbH

Slope stabilisation using soil nailing and a shotcrete shell

Rehabilitation works along the Felderbach stream

The damaged section was located immediately adjacent to the course of the Felderbach stream. In addition to restoring the stability of the road structure, further safety measures were required along the slope. In the central section of the route, a tangential bored pile wall was also planned to protect the road structure from further impacts from the watercourse in future. Before further roadworks could begin, the slope first had to be stabilised and prepared for the subsequent construction phases.

Soil nailing with a shotcrete lining

To temporarily stabilise the slope, it was first excavated to a depth of around 5 m. The slope was then stabilised using soil nailing with a shotcrete lining. The slope stabilisation was carried out in a total of four work layers. Each layer was stabilised using 7.25 m long ground nails, which were embedded in a 25 cm thick reinforced shotcrete shell. The shotcrete structure was adapted to the existing slope geometry and forms the basis for further work on the slope.

Work under constrained conditions

Only limited working space was available along Fellerstraße for the construction of the planned bored pile walls. Consequently, the stabilisation measures had to be carried out initially above the area where construction work would later take place. Furthermore, site logistics were influenced by local conditions. Due to land ownership issues, it was not possible to construct an access road on the valley side. The entire construction site was therefore accessed and supplied via Fellerstraße. Material transport, movement of equipment and work processes were adapted to the available space.

Preparations for the subsequent construction phases

The Soil nailing and the shotcrete lining served to stabilise the slope during the subsequent work on the road and the civil engineering structures. Step by step, this laid the foundation for the further measures to restore Fellerstraße, as well as for the subsequent construction of the bored pile walls in the area of the damaged section.

Foundation for the road’s rehabilitation

Even before traffic can use the route again, the embankment areas have been stabilised and the conditions for further construction work have been created. The installation of the Soil nailing, the shotcrete lining and the preparatory safety measures have laid the foundation for the rehabilitation of the L924 in Velbert. This marks the restoration of a further section of the transport infrastructure along the Felderbach.

What ultimately counts in the construction business is successfully completed projects. PORR has many of these.