Foundations

Stemwede
Wind farm

Stemwede, Germany / 03.2023 - 07.2023

A wind farm comprising ten wind turbines has been built in Stemwede, North Rhine-Westphalia. The turbines have hub heights of around 125 metres and, together, form a wind farm with a capacity of 45 MW. PORR special civil engineering region Nord manufactured a total of 380 Frankipiles NG® for the deep foundations of the turbines.

Picture of a special civil engineering pile driver; the pile driver stands on the round platform for the wind turbine; a worker stands in front of the pile driver
© PORR

Facts & Figures


Company

PORR Spezialtiefbau GmbH

Type

Foundations

Runtime

03.2023 - 07.2023

Principal
enercity Erneuerbare Projekte GmbH & Co. KG

Deep foundations for 10 wind turbines using 380 Franki piles

Foundations for ten wind turbines

The wind farm comprises ten wind turbines manufactured by Nordex. Even before the towers, nacelles and rotors could be erected, the foundations for the structures were laid deep in the subsoil. For each foundation, 30 Frankipiles NG® with a diameter of 51 cm were installed. A further eight piles per site were required for the crane foundations. In total, 380 piles were produced for the wind turbine foundations. The piles transfer the loads from the turbines into load-bearing soil layers and form the basis for the subsequent foundation and tower construction work.

Subsoil improvement for the pile foundations

The upper soil layers consisted of humus-rich topsoil, loose sands, humus-rich silts as well as silty sands. These were followed predominantly by layers of sand with medium density. Subsoil improvement measures were carried out in certain areas as part of the foundation works. This involved pre-compacting the gravel both above and below the pile installation depth. The measures were tailored to the ground conditions and the requirements of the wind turbines.

Frankipiles for foundations and crane sites

The Frankipile NG® from the Greenpile® product family of PORR Spezialtiefbau was used for the deep foundations. The piles reached lengths of up to around 11 m and were installed for the foundations of the turbines as well as the crane sites. The work was carried out in sections in accordance with the sequence of foundation construction on the wind farm site.

Design and Verification

The design of the external pile bearing capacity was carried out by PORR special civil engineering’s design department. In addition, concrete monitoring measures were carried out. Alongside in-house monitoring, third-party monitoring was conducted by a recognised monitoring body in accordance with the project-specific requirements. The results were used to document the pile foundations that had been constructed.

The foundation for the wind farm

Even before the wind turbines came into view and began to shape the landscape, the foundations for the structures were being laid beneath the surface. With the installation of 380 Frankipiles NG® piles, up to 11 metres in length, as well as the foundations for ten wind turbines, the groundwork was laid for the wind farm’s subsequent construction phases. Between the foundations, crane sites and tower locations, the foundations for the Stemwede wind farm were thus established.

What ultimately counts in the construction business is successfully completed projects. PORR has many of these.