SuedLink Elbe crossing ElbX

The SuedLink wind power transmission line is a planned direct current link between northern and southern Germany. According to the project developer, it is intended to transport electricity from renewable energy sources in northern Germany to consumption centres in the south. The project also involves an underwater crossing beneath the River Elbe. TenneT Germany has commissioned PORR to construct a 5.2 km-long tunnel between Schleswig-Holstein and Lower Saxony. High-voltage direct current (HVDC) cables are to be routed through the tunnel in future. The structure is being constructed at a depth of around 40 m using mechanical tunnelling with segmental lining. Various PORR specialist departments are involved in the project, including tunnelling, structural engineering and special civil engineering, as well as pde Integrale Planung, which is responsible for overall BIM coordination.

The project in pictures.
Our videos on the ElbX Elbe crossing.

A selection of images.
Bild von oben; es zeigt den Platz wo später der Zielschacht entsteht
September 2023

The target shaft is being constructed here in Lower Saxony near Wischhafen.

The picture shows a bird's eye view of the tunnel boring machine and the cutting wheel. A man stands next to it and monitors the assembly.
November 2024

The tunnel boring machine and the cutting wheel

The image shows a slotted wall grab currently in use. Green meadows can be seen in the background.
April 2025

Diaphragm wall works for the target excavation pit

Interior view of a tunnel with narrow-gauge tracks in the centre
December 2025

50 per cent of the tunnel has been excavated

The image shows the excavation pit from the side. You can see that the right-hand side is filled with blue water. Construction machinery and cranes are standing around it.
January 2026

The main excavation pit for the shaft building in Wischhafen is complete.

The project.