Munich
Construction pits and DSV underpinning for L137
Munich, Germany / 06.2022 - 09.2022
A new residential and commercial building has been constructed on Landsberger Straße in Munich’s Westend district, between two existing buildings. For the new development, PORR special civil engineering excavated a construction pit measuring approximately 500 m² and 5.2 m deep. In addition to carrying out the special civil engineering works, PORR was also responsible for planning the construction pit stabilisation and underpinning.
Facts & Figures
Company
PORR Spezialtiefbau GmbH
Type
Turnkey construction pits
Runtime
06.2022 - 09.2022
Excavation stabilisation and underpinning for a new building in the city centre
The construction pit was shored on three sides using back-anchored DSV units. On the street side, a back-anchored sheet pile wall with shotcrete infill was used. DSV underpinning was carried out to protect the adjacent existing buildings. The work took place under the constraints of a confined inner-city environment. A site area of only around 30 m² as well as existing underground structures required precise coordination of the construction processes. To this end, compact equipment was used and the works were adapted to the local conditions.
Low-vibration specialist civil engineering works
The construction pit was constructed using low-vibration and noise-reduced methods. This was particularly important given the immediate proximity to existing buildings and the inner-city location. The chosen methods were tailored to the site’s constraints. As part of the site organisation, work processes were also aligned with the DGNB guidelines for construction sites. This included organisational measures on site as well as taking project-specific requirements into account during the execution of the specialised civil engineering works.
The foundations for the new development on Landsberger Straße
The excavation of the construction pit, the installation of the deep foundation underpinning (DSV) and the shoring of the construction pit laid the groundwork for the subsequent structural work. Even before the new residential and commercial building could enhance the streetscape, the structural foundations for it had already been laid underground.