Old Golm
âAlte Ziegeleiâ municipal waste tip
FĂŒrstenwalde, Germany / 04.2020 - 10.2021
On behalf of KWU Entsorgung, a municipal enterprise of the Oder-Spree district, PORRâs EisenhĂŒttenstadt branch carried out work on the surface sealing and reclamation of the âAlte Ziegeleiâ landfill site in Alt Golm near FĂŒrstenwalde. The project involved creating a permanent surface sealing layer covering an area of around 4.5 ha, as well as upgrading an existing temporary surface cover over a further 2.1 ha. The scope of work also included adapting the gas collection system, constructing a perimeter trench around the landfill site, and relocating and grading waste and construction rubble.
Facts & Figures
Company
PORR Verkehrswegbau GmbH
Type
Landfill operations
Runtime
04.2020 - 10.2021
Surface sealing of approximately 6.6 ha of landfill site
Reclamation of a former municipal waste landfill
The âAlte Ziegeleiâ landfill was used as a municipal waste landfill between 1969 and 2011. Following its closure, work was carried out to provide a permanent surface seal and to reclaim the site in accordance with the applicable technical and legal requirements.
As part of the project, the site was prepared for the planned aftercare programme and the existing technical facilities were adapted for future use.
Upgrading of the gas and leachate infrastructure
A key component of the project was the adaptation and extension of the existing landfill degassing and leachate management systems. This included the modification of nine gas wellhead shafts, the laying of approximately 1,400 m of gas pipes, as well as the construction of eight leachate wells. This work was supplemented by the construction of approximately 430 m of sealed landfill perimeter trench. The surface sealing comprises gas-tight and water-impermeable components. In addition, facilities for monitoring landfill gases as well as for the collection and discharge of leachate were incorporated.
Work carried out as part of landfill aftercare
In addition to installing the DK 2-class landfill sealing system, the project also involved the relocation and grading of approximately 24,000 mÂł of waste and construction rubble. Machinery fitted with protective ventilation was used for this work. The various construction works were integrated into the landfillâs existing systems and tailored to the requirements of long-term aftercare.
Technical infrastructure for the siteâs future development
The work at the âAlte Ziegeleiâ landfill site combines traditional earthworks and civil engineering with the requirements of landfill construction. In addition to the installation of the surface liner, the project focused in particular on adapting the gas and leachate infrastructure, as well as preparing the site for further reclamation and aftercare.