Straubing
Port of Straubing Sand
Straubing, Germany / 09.2022 - 10.2023
As part of the Danube expansion project between Straubing and Vilshofen, the harbour basin at Straubing-Sand is being deepened. The port is situated on one of Germany’s major waterways and serves as a key transhipment point between water, rail and road. The deepening of the harbour bed is changing the structural requirements for the existing harbour structures. To reinforce the existing sheet pile walls, PORR special civil engineering Stuttgart was commissioned by the Straubing-Sand Harbour Association to install grouted permanent anchors. The work formed a key part of the preparatory measures for the subsequent deepening of the harbour basin.
Facts & Figures
Company
PORR Spezialtiefbau GmbH
Type
Foundations
Runtime
09.2022 - 10.2023
Permanent anchors ensure the structural integrity of the sheet pile walls
Permanent anchors ensure the structural stability of the sheet pile walls
Upgrading of the Danube waterway
The upgrading of the Danube between Straubing and Vilshofen involves various measures along this stretch of the river. In addition to flood protection, the project also aims to further improve conditions for shipping. At Straubing-Sand harbour, the deepening of the harbour basin necessitates additional safety measures. As the harbour bed will be deepened at a later stage, the existing sheet pile walls will be subjected to greater stress and therefore had to be structurally reinforced before dredging work began. Even before the harbour bed was deepened, the necessary preparations were made along the quay wall for the subsequent construction phases.
Permanent anchors for the sheet pile walls
The structure was reinforced using an additional anchor course comprising a total of 1,076 grouted permanent anchors. The anchors were installed at intervals of one metre and range in length from around 18.50 m to 29 m. Anchor bars with diameters of 40 mm, 50 mm and 63.5 mm were used. As the anchor heads were positioned within the sheet pile troughs, there was no need for additional bracing. The permanent anchors complement the existing structure and contribute to the load-bearing capacity of the sheet pile walls.
Work carried out from the water
To minimise disruption to ongoing port operations, the anchoring work was carried out entirely from a work platform on the water. A work pontoon measuring approximately 42 × 12 m was used for this purpose. Materials, equipment and building supplies were transported to the work area via a supply pontoon. The individual construction phases were coordinated with the constraints of port operations. This enabled the sheet pile walls to be reinforced directly along the quay wall without any further interference with the port facilities on land.
Construction between waterways and natural areas
The works took place within an active port facility and, at the same time, in an environment subject to nature conservation requirements. The material produced during drilling was collected on pontoons, transported ashore and processed there. Furthermore, the works in certain areas had to be coordinated to meet specific time constraints, as adjacent areas are situated within a bird sanctuary. For the special civil engineering works, the site was awarded the ‘Sustainable Construction Site – Special Civil Engineering’ pre-certificate by the German Sustainable Building Council (DGNB). The assessment took into account, amongst other things, aspects of site organisation, resource management, health and safety, as well as construction execution. The individual construction phases were planned and carried out in accordance with local conditions.
Basis for deepening the harbour basin
Even before dredging work began to lower the harbour bed, the structural foundation for the next expansion stages was created along the existing quay wall. The installation of 1,076 grouted permanent anchors laid the groundwork for reinforcing the harbour facilities. This created a further section of the infrastructure for the future development of the Straubing-Sand harbour on the Main-Danube Canal.