Stuttgart 21 – Concrete base Filder tunnel
Stuttgart, Germany / 01.2016 - 04.2016
On the major construction site of Stuttgart 21, ÖBA manufactured a concrete tunnel slab with a durable water trough and a cross section of 5.5 m.
The approximately 4.0 km long stretch with a cross section of approximately 4.0 m³/running metre was realised with an average performance of 150 running metres/day.
Facts & Figures
Company
ÖBA – Österreichische Betondecken Ausbau GmbH
Type
Special concrete construction
Runtime
01.2016 - 04.2016
High tech underground.
This enormous achievement was made possible by a slip-form paver. It moves along the segment with a track system angled at 40°.
Technical equipment and experience were significant criteria for the customer in assigning this major project to ÖBA.