The historic quay wall on the Zollkanal is situated within the core zone of the Speicherstadt UNESCO World Heritage Site and is around 130 years old. Damage to the structure, including cracks, deformations and localised settlement, was identified as a result of tidal forces as well as long-term use. PORR special civil engineering planning developed the detailed design and structural engineering concepts for the rehabilitation of the quay wall.

3D graphic of the project
© PORR

Facts & Figures


Company

PORR Spezialtiefbau Planung GmbH

Type

Planning

Runtime

01.2021 - 07.2021

Principal
PORR Spezialtiefbau GmbH

Planning the quay wall renovation in the UNESCO World Heritage Site, the Speicherstadt

Historic quay wall in the Speicherstadt area

The quay wall is situated on the Zollkanal within Hamburg’s Speicherstadt. Investigations revealed damage to the existing structure. In particular, sections of the tie-beams in the water-facing timber sheet pile wall were missing, which had led to subsidence on the landward side. A refurbishment concept was developed for the repair work, which integrates the existing quay wall into the new structure.

Back-anchoring with micro piles

The renovation concept involves back-anchoring the quay wall using micro piles. The micro piles will first be connected to the existing structure. The detailed design and structural analysis for the anchoring were carried out by PORR special civil engineering planning. In addition, test loads on the structural piles as well as acceptance tests are planned.

Specially developed drilling rig

A project-specific drilling rig was designed for the installation of the anchoring system. The structure will be mounted directly onto the existing quay wall and will serve as a working platform for the drilling operations. The drilling rig was designed taking into account the existing structural layout as well as the spatial constraints along the Zollkanal. Micro piles with sleeve couplings. Once the micro piles have been installed, a new sheet pile wall will be driven in on the water side in front of the existing quay wall. The micro piles can then be extended towards the water using sleeve couplings and connected to the new structure. Finally, the construction of a reinforced concrete quay head with a facing shell is planned. The facing shell will be modelled on the existing design of the historic quay wall.

Digital planning with a 3D model

A three-dimensional model was created for the planning. In addition to the existing district heating tunnel and the anchors on the opposite side of the St Annen Fleet, the model included these elements. The model was used to coordinate the structure’s geometry and the spatial arrangement of the various structural elements and infrastructure pipelines.

Basis for the rehabilitation of the quay wall

The planning of the micro-pile anchoring, the sheet pile wall construction as well as the digital modelling laid the groundwork for the rehabilitation of the historic quay wall on the Zollkanal. These measures are part of the rehabilitation of a structure within the UNESCO World Heritage Site, the Speicherstadt.