Strullendorf
Single-chamber economiser
Strullendorf, Germany / 04.2024
The Strullendorf lock is situated on the Main–Danube Canal, a few kilometres south of Bamberg. Commissioned in 1968, the structure is one of the older locks on the canal and, via its lock chamber, connects different water levels along the waterway. During a structural inspection, signs of corrosion were detected on the reinforcement in the eastern chamber wall. To reinforce the structure, PORR special civil engineering was commissioned by the RÖDL BAU.GRUPPE to install permanent anchors in the area of the wall head.
Facts & Figures
Company
PORR Spezailtiefbau GmbH
Type
Rehabilitation
Runtime
04.2024
Permanent anchors reinforce the lock chamber on the Main-Danube Canal
Reinforcement of a lock system
The Strullendorf lock is designed as a single-chamber economy lock with an attached stilling basin. It has a useful chamber length of 190 m, a useful width of 12 m as well as a head of 7.4 m, with a total height of 12.61 m. As part of the repair works, 40 permanent single-rod anchors were installed. Each anchor is 21.40 m long and serves to provide additional structural reinforcement for the eastern chamber wall. Even before the actual repair measures could be carried out on the lock, this created the conditions necessary for further work on the structure.
Grouted anchors for the wall crown
The reinforcement measures focused on the upper section of the chamber wall. It was here that the permanent anchors were installed and permanently connected to the structure. The anchors transfer forces within the structure and complement the existing load-bearing members of the lock wall. They thus form an integral part of the structural reinforcement of the lock. The work was carried out during a scheduled closure of the lock to shipping traffic.
Working platform above the lock chamber
A particular challenge was positioning the drilling rigs on the lock wall. To achieve this, a temporary working platform was developed without the need to fill the lock chamber or use floating work platforms. The structure consisted of precast concrete elements as well as a combination of steel beams and steel plates. It was specifically designed for the work on the lock chamber and enabled the anchors to be installed along the top of the wall. This created a working platform directly adjacent to the structure, tailored to the spatial constraints of the lock.
Work between waterway traffic and lock operations
The work was carried out within an existing waterway facility. The individual construction phases were coordinated with the schedule of the repair work as well as the temporary closure of the lock. A project-specific risk assessment was drawn up for the temporary working platform. The work was carried out on the basis of this planning as well as the site-specific constraints. Step by step, this led to the reinforcement of a structure that has been part of the Main–Danube Canal for decades.
Foundation for further repair works
Even before the lock is reopened to shipping, permanent anchors are being installed to provide additional load-bearing elements within the structure. The installation of the 40 single-bar anchors laid the foundation for further repair works on the eastern chamber wall. This marks the restoration of another section of the Main–Danube Canal’s technical infrastructure.